Ardooie_01 · POP_002
POP sheet: everything about this POP in one place.
Technical preparation
- Redesign
- To do
- Druktest
- To do
- POC/DP plaatsen
- To do
- Next delivery
- 20/11/2026
Construction
- Trenching
- 8 984.4 m · 65%
- Blaaswerk
- —
- Cables OK
- 0 / 0
- Left to blow
- 0 m · 0/0 finished routes
Blowing plans
📎 Legplan · 10/07 SharePoint
Synergies
Cables in SPER 0 · KABELWERKEN
No cable in SPER for this POP.
Cables in synergy 0 · KABELWERKEN
No cable in synergy for this POP.
Cable routes 0 · open in Cable to plan →
No route for this POP.
Interventions 0
No intervention for this POP.